Live updates, milestones and site photography from our active construction projects.
Solar-Powered Boreholes & Stanchion
Ogun State • Ogun State Government • ₦19.2M
Overall Progress
60%
Started 2024
Milestones
- ✓Site mobilisation & survey
- ✓Borehole drilling (Phase 1)
- ✓Solar panel installation
- Stanchion fabrication & erection
- Commissioning & handover
Latest Update
Drilling and solar installation are complete. Stanchion fabrication is underway and erection is scheduled to commence shortly.
Site Photos


More site photos will appear here as the project progresses
Commercial Development, Isheri North
Lagos • JIN Goshen Nigeria Ltd • ₦50M
Overall Progress
35%
Started 2024
Milestones
- ✓Site clearance & setting out
- ✓Foundation works
- Substructure & ground floor slab
- Superstructure (blockwork & columns)
- Roofing & finishing works
- MEP fit-out & handover
Latest Update
Foundation works are complete. Ground floor slab preparation is in progress. Materials for the superstructure phase have been procured and are on site.
Site Photos


More site photos will appear here as the project progresses
See Our Completed Projects
Browse the full portfolio of projects we have delivered for government agencies, corporations and private clients across Nigeria.